Premiere today in the demolitions of arbitrary buildings in Attica

--

Today, Wednesday (1/11), the Ministry of Environment and Energy plugged in the implementation program of the arbitrary demolition protocols, which are final.

Specifically, as the Ministry of the Interior states in its announcement, the pilot program begins in Attica with the demolition of 16 properties located on seashores, beaches and forest areas and is to be extended to other areas of the country.

The beginning was made today, with the demolition of a property – within the Parnitha National Forest in the location “Kalamara”, District of the Municipality of Phylis – which is expected to be completed tomorrow, Thursday.

It is noted that the program is financed by the Green Fund and implemented by the decentralized administrations.

“The principle of legality is a prerequisite for the correct application of the urban planning legislation and for the reforms that must be made in the urban planning legislation”, emphasized the Minister of Environment and Energy, Thodoros Skylakakis.

The list of 16 properties in Attica that will be demolished by the end of 2023

1st DEMOLITION

  • No. Arbitrary Demolition Protocol: 2588/19-6-2008
  • Area: Tribe
  • Start of demolition: 1/11/23 day Wednesday
  • Completion of demolition: 2/11/23 day Thursday
  • Demolition duration: 2 days

2nd DEMOLITION

  • No. Arbitrary Demolition Protocol: 880/27-12-1994
  • Area: Stop
  • Start of demolition: 2/11/23 day Thursday
  • Completion of demolition: 3/11/23 day Friday
  • Demolition duration: 2 days

3rd DEMOLITION

  • No. Arbitrary Demolition Protocol: 1582/12-4-2002
  • Area: Penteli
  • Start of demolition: 3/11/23 day Friday
  • Completion of demolition: 6/11/23 day Monday
  • Demolition duration: 4 days

4th DEMOLITION

  • No. Arbitrary Demolition Protocol: 1135/19-3-2002
  • Area: Round
  • Start of demolition: 7/11/23 day Tuesday
  • Completion of demolition: 8/11/23 day Wednesday
  • Demolition duration: 2 days

5th DEMOLITION

  • No. Arbitrary Demolition Protocol: 2944/22-12-2010
  • Area: Rethi Drakou
  • Start of demolition: 8/11/23 day Wednesday
  • Completion of demolition: 10/11/23 day Friday
  • Demolition duration: 3 days

6th DEMOLITION

  • No. Arbitrary Demolition Protocol: 2945/22-12-2010
  • Area: Rethi Drakou
  • Start of demolition: 9/11/23 day Thursday
  • Completion of demolition: 11/11/23 day Saturday
  • Demolition duration: 3 days

7th DEMOLITION

  • No. Arbitrary Demolition Protocol: 1002/15-4-2003
  • Area: Barbuchana Drapo
  • Start of demolition: 13/11/23 day Monday
  • Completion of demolition: 11/14/23, Tuesday
  • Demolition duration: 2 days

8th DEMOLITION

  • No. Arbitrary Demolition Protocol: 1319/27-12-1994
  • Area: Skalopati Agios Charalambos
  • Start of demolition: 15/11/23 day Wednesday
  • Completion of demolition: 18/11/23 Saturday
  • Demolition duration: 4 days

9th DEMOLITION

  • No. Arbitrary Demolition Protocol: 3547/6-8-2003
  • Area: Ipiti
  • Start of demolition: 16/11/23 day Thursday
  • Completion of demolition: 17/11/23 day Friday
  • Demolition duration: 2 days

10th DEMOLITION

  • No. Arbitrary Demolition Protocol: 530/00/19-10-2001 2262/2000/30-10-2001
  • Area: Terpsithea/Gyrisma Terpsithea
  • Start of demolition: 20/11/23 day Monday
  • Completion of demolition: 22/11/23 day Wednesday
  • Demolition duration: 3 days

11th DEMOLITION

  • No. Arbitrary Demolition Protocol: 1098/PE/9-2-2016
  • Area: Hamolia Vravrona
  • Start of demolition: 20/11/23 day Monday
  • Completion of demolition: 20/11/23 day Monday
  • Demolition duration: 1 day

12th DEMOLITION

  • No. Protocol on Arbitrary Demolition: 68/2008, 75/2008, 76/2008, 77/2008, 61/2008, 62/2008, 63/2008, 69/2008, 73/2008, 74/2008, 64/2008, 65/ 2008, 67/2008
  • Area: Agia Triada Vourkario
  • Start of demolition: 20/11/23 day Monday
  • Completion of demolition: 30/11/23 Thursday
  • Demolition duration: 11 days

13th DEMOLITION

  • No. Arbitrary Demolition Protocol: 4073/94/15-3-1995
  • Area: Lordou Vgena Varela
  • Start of demolition: 23/11/23 day Thursday
  • Completion of demolition: 25/11/23 Saturday
  • Demolition duration: 3 days

14th DEMOLITION

  • No. Arbitrary Demolition Protocol: 1536/93/19-12-1994
  • Area: Agia Kyriaki
  • Start of demolition: 27/11/23 day Monday
  • Completion of demolition: 29/11/23 day Wednesday
  • Demolition duration: 3 days

15th DEMOLITION

  • No. Arbitrary Demolition Protocol: 3840/98/17-2-1999
  • Area: Vorineza
  • Start of demolition: 30/11/23 day Thursday
  • Completion of demolition: 2/12/23 day Saturday
  • Demolition duration: 3 days

16th DEMOLITION

  • No. Arbitrary Demolition Protocol: 4484/29-9-2003
  • Area: Harvati Porto Rafti
  • Start of demolition: 4/12/2023 day Monday
  • Completion of demolition: 9/12/23 day Saturday
  • Demolition duration: 6 days
Follow iEidiseis.gr on Google News

The article is in Greek